Skip navigation

FMEA #:11 |Procurement Process

FMEA #:11 |Procurement Process

FMEA Ref #: 
11
Select FMEA Basis: 
Process Design
Related Process: 
Procurement
Responsibility: 
Developer
Responsibility: 
Chairman
Status: 
Active
Rating (Six-Sigma Compelled)
Severity of Effect: 
5. Cause a loss of performance which is likely to result in a complaint
Likelihood of Occurrence: 
7. Once per month
Ability to Detect: 
1. Defect is obvious and can be kept from affecting the customer
Control Estimated Cost $: 
5,000.00 USD
RPN Value
The Risk Priority Number RPN = The Severity ranking X the Occurrence ranking X the Detection ranking. The RPN can range from a Low =(1-300) Medium=(301-600) and High =(601- 1,000). Develop an Action Plan to reduce risks with unacceptably high RPNs.
RPN (Risk Priority Number): 
35
Recommended Action: 
Create Action Plan