ISO 9001:2008 Reference
8 Measurement, analysis and improvement
8.2 Monitoring and measurement
Tagged "8.2.2 Internal audit"
Posts
Files
Help
There are no files tagged with this term.
Need help?
8.2.2 Internal audit
The organization shall conduct internal audits at planned intervals to determine whether the quality management system
a) conforms to the planned arrangements (see 7.1), to the requirements of this Int.Standard and to the quality management system requirements established by the organization, and
b) is effectively implemented and maintained.
An audit programme shall be planned, taking into consideration the status and importance of the processes and areas to be audited, as well as the results of previous audits.
A documented procedure shall be established to define the responsibilities and requirements for planning and conducting audits, establishing records and reporting results.
Records of the audits and their results shall be maintained (see 4.2.4).
The management responsible for the area being audited shall ensure that any necessary corrections and corrective actions are taken without undue delay
Follow-up activities shall include the verification of the actions taken and the reporting of verification results (see 8.5.2).